Jubilee Primary School

Hammer
Type

Education

User
Client

Jubilee school Sensory Space & Classroom refurbishment

Clock
Duration

6 Weeks School summer holiday Shut down

Pound sign
Value

£250K

Introduction / Scope:

Clive Graham Associates were appointed by Ingleton Wood to undertake strip and refurbishment of a new Sensory Space room for children with severe learning difficulties, new multi-use classroom with sliding wall separation abilities, new ceilings and AV components and male and female student and teacher WCs refurbishment within Jubilee school Brixton Tulse Hill. The works were programme for completion during the school summer holiday shut down and CGA were supported by the School, Ingleton Wood and our design team to make the project a success.

 

Challenges:

Introduction of new roof mounted plant to an existing roof with no direct access for material citing or access for the installation trades and then maintenance team thereafter.

The existing roof structure needed to have anew steel support system introduced to the existing beams through the existing roof finishes and waterproofing to allow for the new plant load requirements

 

Solution:

CGA undertook with the aid of the tender client design team a full design of new space for access to the roof, Existing drainage design adaptions through to components for the project.

We worked closely with our contract lift company and undertook a full lifting plan for means of citing the plant and our steel contractor for a bespoke access method and steel support framework for the new mechanical plant being positions on the roof.

We had to undertake cutting through the existing roof finish for service penetration for duct and electrical supplies to the roof and then weather the aperture upon completions whilst still maintaining the roofs integrity.

 

Materials and components:

1.       New sliding London wall system in multi-use classroom

2.       New Sensory room for students with required sensory needs.

3.       New partitions wall layout

4.       Introduction of additions and alteration to existing public health and drainage

5.       Sensory stimulating controllable lighting system

6.       New ceilings throughout

7.       New IPS cubicle system in male and female student WCs

8.       New mechanical services

9.       Electrical small power and lighting adaptation and introduction

10.     Floor finishes

11.     New doors with child proofing treatment

12.     New emergency lighting and panic alarms

13.     AV and interactive teaching presentation methods

14.     Soft furnishes and seating to Sensory Room

15.     New blinds