Greenwich Peninsular C4 Canteen

Hammer
Type

Commercial Fit-out

User
Client

JCT Design & Build

Clock
Duration

Phase 1: 6 Week Phase 2: 4 Weeks

Pound sign
Value

£440k

Scope & Overview:

This project was undertaken in two phases to meet the client's aspirations for the 2022 World Cup. The following phase was completed on schedule. The scope of the project included a refresh of the entire finishes of the C4 Canteen areas on the ground floor and the mezzanine.

  1. Additional Lighting
  2. Heating Poles
  3. Floor Paint
  4. New Upstand Balcony
  5. Internal Linings
  6. New DB and Armoured Power Supply to the Mezz Floor for Heating Pole
  7. Fire Alarm Alterations
  8. Roller Shutter
  9. New Bar Top
  10. New Bar Front Tiles, Feature Signage, and Kick Bar
  11. Foot Rail Around the Entire Building
  12. New Balustrade Hand Rail to Mezz with Tying Back to Structure
  13. Poli-carb Signage
  14. Feature Lighting
  15. Festoon Lighting
  16. Actuator Steel Covers
  17. Canteen Retail Unit Power Supplies
  18. Canteen LED Feature Lighting to External
  19. External Plinth for Cistico Signage Screen