CGA was appointed to carry out a specialist structural project at Harlow College (Stansted Airport College), comprising the creation of a new mezzanine floor to maximise the use of the existing workshop space. The project was delivered within an 8-week programme, with careful coordination to minimise disruption to ongoing college operations.
Scope of Works
Structural Steelwork
The installation of structural steelwork formed the primary element of the project, providing the support structure for the new mezzanine deck and ensuring full structural compliance throughout.
Service Adjustments
Existing services were adjusted and reconfigured to accommodate the new floor level, maintaining operational continuity across the workshop space during and after the works.
New Metal Staircase
A new metal staircase was constructed to provide safe and compliant access between the ground floor and the new mezzanine level, meeting all relevant building regulations and health and safety requirements.
Results
The project was completed on programme within 8 weeks, delivering a functional new mezzanine level that significantly expands the usable space within the college's workshop. The works were carefully coordinated to avoid disruption to college operations, demonstrating CGA's ability to deliver structural projects efficiently in a live education environment.
CGA completed multi-phased refurbishments at St Louis Catholic Primary School, including new toilets, reception, and converting an external courtyard into teaching space. The project was delivered on time, enhancing the school's functionality.
CGA completed recladding and remedial works at Park View School's sports hall, ensuring compliance with safety standards, improved functionality, and enhanced aesthetics. The project was delivered on time and within budget.
CGA completed a comprehensive £400k refurbishment of Wentworth Primary School's sports hall, enhancing safety, energy efficiency, and modern facilities within a 14-week timeline.