Newstead Wood School Library

Hammer
Type

Education

User
Client

Newstead Wood Girls School - United Learning

Clock
Duration

6 weeks school summer holiday shut down for each project

Pound sign
Value

£200K

Introduction / Scope:

We undertook a repeat business with United Learning to fit-out the Newstead Wood Girls School library

Challenges: During the soft strip and demolition we discovered some bitumen asbestos when removing existing floor finishes that was not on the client demolition and refurbishment survey

Solution: We absorbed the delay through total segregation of the floor finish removal and maintain original programme duration with minor disruption to the programme.

Materials and components:

Asbestos removal (Priced removal as variations)Strip out of structural wallsStrip out of existing heating systemsGeneral soft strip demolition through to get back to fabricFloor finishesNew door installationNew skirtingFire alarm adaptations and upgradesNew small power in dado trunkingNew lighting schemeAcoustic baffle ceiling bafflesPaint finishes throughout• Client FF&E

 

Materials and components:

  1. Asbestos removal (Priced removal as variations)
  2. Strip out of structural wallsStrip out of existing heating systems
  3. General soft strip demolition through to get back to fabricFloor finishes
  4. New door installation
  5. New skirting
  6. Fire alarm adaptations and upgrades
  7. New small power in dado trunking
  8. New lighting scheme
  9. Acoustic baffle ceiling baffles
  10. Paint finishes throughout
  11. Client FF&E